Deze Energy Corp. Ltd. Taltson Hydroelectric Expansion Project - EA0708-007 [2007]
Project Description
This is a hydroelectric project that adds a new 36 megawatts of power generating capacity to the existing 18 megawatt Taltson Twin Gorges Plant and includes transmission lines through the Akaitcho region and Monfwi Gogha De Niitlee
Type: Environmental assessment - Completed and waiting for a ministerial decision
Status: Report sent to INAC Minister, August 6, 2010
Document Summary
| 19 | Preliminary screening |
| 4 | EA start up |
| 15 | Scoping |
| 18 | Terms of Reference |
| 2 | Developer's Assessment Report |
| 24 | Information requests |
| 38 | Technical sessions |
| 13 | Technical reports |
| 2 | Pre-hearing conference |
| 21 | Public hearings |
| 4 | Report of Environmental Assessment |
| 2 | Post REA materials and consult to modify (current stage) |
| Minister's decision and final measure | |
| 165 | Additional information |
| Hearing follow-up | |
| Report of Environmental Review | |
| Post-REIR materials and Consult to Modify | |
| 327 | Total Number of Documents |