De Beers Canada Inc. Gahcho Kue Diamond Mine - EIR0607-001 [2006]
Document List: Additional information
Note to File- Temporary Contact Info
February 5th, 2010Review Board correspondence, notes and requests
Until February 19th 2010, all contact regarding this environmental impact review should be directed to Nicole Spencer, Environmental Assessment Officer (Tel: (867) 766-7062; nspencer@reviewboard.ca ).
Panel to De Beers re EIS delay May 29 2009
June 1st, 2009Review Board correspondence, notes and requests
Correspondence from the Gahcho Kue Panel to De Beers Canada requesting additional information and scheduled updates regarding progress toward issuance of the developer's Environmental Impact Statement.
Correspondence on participant funding during EIA
September 16th, 2008Other
Correspondence of June 16, 2008, from Mackenzie Valley Review Board to Minister of Indian and Northern Affairs Canada, and response of September 5, 2008 from the Minister. Regarding request for participant funding, including for the Gahcho Kue Panel Review.
2008 news release on panel composition
July 11th, 2008Review Board correspondence, notes and requests
News release original posted on the Review Board's website on July 11, 2008, indicating that Elder Jim Villeneuve of Fort Resolution had replaced Richard Edjericon as a panel member.
DKFN Concerns
December 6th, 2007Party or public correspondence, reports and requests
This is a letter from Deninu Kue First Nation describing concerns related to the Gahcho Kue project.
Site Visit Presentation File #4
November 9th, 2007Developer correspondence, reports and requests
This is the fourth of four files containing the presentation shown to the Panel and staff, during a site visit on Sept. 21, 2007.
Site Visit Presentation File#3
November 9th, 2007Developer correspondence, reports and requests
This is the third of four files containing the presentation shown to the Panel and staff, during a site visit on Sept. 21, 2007.
Workshop Update
November 7th, 2007Developer correspondence, reports and requests
This update from De Beers described changes to its workshop schedule.
Site Visit Presentation File #2
October 30th, 2007Developer correspondence, reports and requests
This is the second of four files containing the presentation shown to the Panel and staff during a site visit on Sept. 21, 2007.
Site Visit Presentation File #1
October 30th, 2007Developer correspondence, reports and requests
This is the first of four files containing the presentation shown to the Panel and staff, and other materials, during a site visit on Sept. 21, 2007. Also shown to the Panel with this presentation was a DVD describing the project. [The DVD is available on the public registry at the Review Board office. To recieve a copy from De Beers, please contact Barbara Zoe, De Beers Canada Public and Corporate Affairs Assistant].
De Beers' EIS Workshops
October 29th, 2007Developer correspondence, reports and requests
This letter states that the EIS workshops planned by De Beers will be rescheduled to dates to be announced early in 2008. Also attached is the original Sept. 25, 2007 letter announcing the workshops.
e-mail - Response to Message of June 28 2007
July 10th, 2007Review Board correspondence, notes and requests
Response to letter from NWT Metis Nation of June 28, 2007 regarding consultation between DeBeers and the Fort Resolution Metis Council.
Letter from NWTMN to MVEIRB re: Consultation between developer & party
June 28th, 2007Party or public correspondence, reports and requests
This letter outlines the Northwest Territory Metis Nation's opinion that DeBeers Canada has not adequately consulted with them regarding their Gahcho Kue project.
Note to File, NWTMN
June 28th, 2007Review Board correspondence, notes and requests
Note to file regarding correspondance received from the NWTMN on June 28, 2007.
DeBeers letter no appeal
April 13th, 2007Developer correspondence, reports and requests
Letter from DeBeers indicating that DeBeers will not be appealing the NWT Supreme Court decisions upholding the EIR order.
NWT Supreme Court Decision on judicial review
April 4th, 2007Other
The NWT Supreme Court upheld the MVEIRB's order to undertake an environmental impact review.
Response to Chief Sayine DKFN re Gacho Kue Consultation Dec 6, 2006
December 6th, 2006Review Board correspondence, notes and requests
Response to Deninu Kue First Nation letter to GNWT, INAC, DeBeers and MVEIRB of November 30, 2006 regarding consultation requirements.
DKFN letter re consultation for Gahcho Kue
November 30th, 2006Party or public correspondence, reports and requests
Letter from Deninu Kue to GNWT, INAC, DeBeers, and MVEIRB regarding consultation requirments.
letter - judicial review notification
August 3rd, 2006Review Board correspondence, notes and requests
Cover letter to distribute DeBeers' application for judicial review to parties.
EIR judicial review application
July 28th, 2006Developer correspondence, reports and requests
Application to NWT Supreme Court for a judicial review of MVEIRB's order to conduct an EIR. Filed by DeBeers Canada.
chamber of mines letter re EIR order
June 20th, 2006Party or public correspondence, reports and requests
Letter from chamber of mines expressing concern that the Review Board's order for an environmental impact review was unneccessary.
Total Number of Documents: 21